Hope everyone is enjoying this wonderful Portland weather that we are experiencing! On the off chance that rain, hail, snow and freezing temperatures don’t brighten your day; here are some updates on what’s going on with our build-out and potential opening date to help lighten your mood!
-Our equipment order from Rouge Fitness was delivered today, all 5,000 pounds of it (1,500 lbs pictured below).
-If everything goes as scheduled, our walls, bathroom, and lighting should all be in by the end of this week. Once that is finished, we’ll have the city come in for our final inspection so that we can officially “occupy” the space!
-Painting, floor installation, and equipment setup should all happen next week.
-Once we receive our occupancy permits we’ll begin running a limited class schedule until we finish everything else up. Meanwhile, we’ll be updating the blog with weekly updates and will post more frequent updates to the CFPD Facebook Page.
Thanks again for all of your patience! This whole process is certainly taking longer than we had anticipated, but we’re certainly happy with how everything is turning out so far and we hope to be opening our doors soon! Until then, stay dry, keep warm, and avoid Girl Scout cookies like the plague (unless they are the Peanut Butter Patties, which are extremely healthy for you… right?).